Construction / Progress Update
Contract No. |
Contract Name |
Contractor |
Contract Award Date |
Completion Date |
Construction Sites |
901 |
Admiralty Integrated Station and SCL Enabling works
901Progress of work
|
Kier-Liang O'Roukre-Kaden Joint Venture |
05/2011 |
2015 |
|
|
Last Updated at : February 2012 |
| |

Harcourt Garden
Piling, excavation and lateral support works as well as diaphragm wall works are in progress.
|
902 |
Nam Fung Tunnel and Ventilation Buildings
902Progress of work
|
Nishimatsu Construction Co. Ltd. |
05/2011 |
2015 |
- Hong Kong Park Ventilation Building
- Nam Fung Portal
- Chung Hom Shan Magazine
|
|
Last Updated at : February 2012 |
| |

Hong Kong Park Ventilation BuildingExcavation and lateral support works are in progress.

Hong Kong Park Ventilation BuildingConstruction of reprovision works for LCSD’s facilities is in progress.

Nam Fung PortalSite formation works are in progress.

Nam Fung PortalTemporary haul road construction is in progress.

Nam Fung PortalExcavation and lateral support works are in progress.

Nam Fung PortalExcavation for the Transition Box is in progress.

Nam Fung PortalConstruction of the Transition Box is in progress.

Chung Hom Shan Temporary MagazineThe temporary magazine is in operation.
|
903 |
Ocean Park Station, Wong Chuk Hang Station, Viaduct and Aberdeen Channel Bridge
903Progress of work
|
Leighton Contractor (Asia) Limited |
05/2011 |
2015 |
- Viaduct Zone B (Near the Aberdeen Tunnel)
- Ocean Park Station
- Viaduct Zone C (Near the Hong Kong Police College)
- Wong Chuk Hang Station
- Nullah
- Viaduct Zone D (From Nam Long Shan Road Cooked Food Market to Holy Spirit Seminary)
- Aberdeen Channel Bridge Section
|
|
Last Updated at : February 2012 |
| |

Viaduct Zone B (Near the Aberdeen Tunnel)Viaduct pier and pile cap construction works are in progress.

Viaduct Zone C (near the Hong Kong Police College)Bored pile construction works are in progress.

Viaduct Zone D (near the Jockey Club Rehabilitation Centre) Bored pile construction works are in progress.

Aberdeen Channel Bridge SectionBored pile and pile cap construction works are in progress.

Ocean Park StationBored pile construction works are in progress

Wong Chuk Hang StationStation columns construction works are in progress.

Nullah Works New nullah walls and construction works for decking are in progress.
|
904 |
Lei Tung Station, South Horizons Station and Tunnels
904Progress of work
|
Leighton - John Holland Joint Venture |
05/2011 |
2015 |
- Ap Lei Chau Cut & Cover Tunnel
- Lei Tung Entrance A
- Lei Tung Entrance B
- South Horizons
- Lee Wing Street Tunnel Portal
|
|
Last Updated at : February 2012 |
| |

Ap Lei Chau Bridge RoadInstallation of pipe piles and ground anchors for a cut and cover tunnel are in progress. Construction of a tunnel box structure was started in February 2012. Demolition of the existing caisson wall will be completed by April 2012.

Lei Tung Entrance ASoil nailing works for slope upgrading were completed in January 2012. Subsequently, the constuction for the second phase of pipe piling will be started.

Lei Tung Entrance BConstruction of the retaining wall at a new bus terminus was completed in February 2012. Subsequently, the road works at the new bus terminus will be started.

Lee Wing StreetSite formation was completed in February 2012. Mechanical excavation for the Lee Wing Street Tunnel will be completed in March 2012. Subsequently, the first blast will be carried out. Construction of the conveyor belt was started in February 2012.
 
South HorizonsPiling works and other utilities works along Lee Nam Road and Yi Lam Road are in progress. Diversion works for water mains at Yuk Kwai Shan and Lee Nam Road are in progress. Site formation for the end plant building was started in January 2012 and erection of the rockfall fence was completed in February 2012.
|
907 |
Wong Chuk Hang Depot Site Formation and Piling
907Progress of work
|
Chun Wo - Hip Hing JV |
05/2011 |
2012 |
- Wong Chuk Hang Depot
- Temporary Bus Terminus
|
|
Last Updated at : February 2012 |
| |

Wong Chuk Hang Depot Site Formation works are in progress.

Wong Chuk Hang DepotThe open blast is in progress.

Wong Chuk Hang DepotPipe pile construction works are in progress.

Wong Chuk Hang Depot Bored pile construction works have been substantially completed.

Nam Long Shan RoadThe utility diversion works are in progress.

Temporary Bus TerminusTemporary bus terminus at Nam Long Shan Road has been in operation since October 2011.
|